If you want to include the total fixture cost in the take-off, you might want to consider creating an assembly that consists of a $1 misc. fixture cost item. 

  • You can create an item titled Misc. Fixture Cost
  • In the item maintenance screen, you would check the checkbox "This is a Zero Labor Item".
  • Enter a material cost of $1
  • Add this item to an assembly titled Misc. Fixture Cost ($1)


By adding this assembly to the take-off screen, you can add the fixture cost as the quantity. For example, if the fixture cost is $10,000, you would enter 10,000 for the Misc. Fixture Cost assembly's quantity in the take-off. This method would add the cost to the total, as well as applying the material tax to the fixture amount.